Earthworks Calculator
Cut & fill analysis with mass haul diagram | End Area + Prismoidal Methods | Ghilani & Wolf Ch.26 | Merritt Civil Engineering Handbook Sec.21
Total Cut Volume
3800.0 m³
End Area Method
Total Fill Volume
2750.0 m³
End Area Method
Net Volume (Cut - Fill)
+1050.0 m³
Surplus material — export needed
Mass Haul Diagram
Cumulative earthwork volume along the alignment. Positive = cut, Negative = fill. Points crossing zero indicate transition between cut and fill zones.
-650
0+000
-550
0+020
350
0+040
1500
0+060
2150
0+080
1900
0+100
1050
0+120
Cut (positive)
Fill (negative)
Volume Comparison by Section
| Section | Cut Area (m²) | Fill Area (m²) | End-Area Vol (m³) | Prismoidal Vol (m³) | Difference (%) |
|---|---|---|---|---|---|
| 0+000 — 0+020 | 5.0 | 37.5 | -650.0 | -650.0 | +0.00% |
| 0+020 — 0+040 | 22.5 | 17.5 | 100.0 | 100.0 | +0.00% |
| 0+040 — 0+060 | 47.5 | 2.5 | 900.0 | 900.0 | +0.00% |
| 0+060 — 0+080 | 57.5 | 0.0 | 1150.0 | 1150.0 | +0.00% |
| 0+080 — 0+100 | 40.0 | 7.5 | 650.0 | 650.0 | +0.00% |
| 0+100 — 0+120 | 15.0 | 27.5 | -250.0 | -250.0 | +0.00% |
| 0+120 — 0+140 | 2.5 | 45.0 | -850.0 | -850.0 | +0.00% |
Cross Section Data Entry
Road Template Settings
Cross Section Data
Format: Chainage (km), Chainage (m), CL RL, Form RL, then L4_off, L4_rl, L3_off, L3_rl, L2_off, L2_rl, L1_off, L1_rl, R1_off, R1_rl, R2_off, R2_rl, R3_off, R3_rl, R4_off, R4_rl
| Ch km | Ch m | CL RL | Form RL | Left Shots (outer→CL) | Right Shots (CL→outer) | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Off | RL | Off | RL | Off | RL | Off | RL | |||||||||